Irion County ISD October 14 2026
Updated: Oct 18
Agenda Analysis | Meeting Review | Meeting Documents | Commentary | Last Meeting

October 14, 2026 at 6:00 PM - Board Meeting
Agenda |
1. Call to Order Speaker(s): Chad Koonce |
2. Opening Ceremonies Speaker(s): Chad Koonce |
3. Student Recognitions Speaker(s): Dr. Jessica Parker |
4. Public Comments Speaker(s): Chad Koonce |
5. Construction Update Speaker(s): Gallagher Construction |
6. Consent Agenda Speaker(s): Chad Koonce |
7. Administration Reports Speaker(s): Dr. Jessica Parker, Dr. Michael Heath, John Morrow, Ben Martin Description: 1. Dr. Jessica Parker (Principal Update) 2. Coach John Morrow (Athletics Update) 3. Ben Martin (Band Update) 4. Dr. Michael Heath (Superintendent Update) |
8. Action Items Speaker(s): Dr. Michael Heath, Alexis Jackson, Gallagher Construction Description: 1. Discuss/Approve ESL Program Evaluation (Presented by Mrs. Jackson) 2. Discuss/Approve FLETCO to handle the renovations of the 1909 building. 3. Report on board member training hours (No Action) |
9. Executive Session Speaker(s): Chad Koonce |
10. Return to Open Session Speaker(s): Chad Koonce |
11. Adjournment Speaker(s): Chad Koonce |
A. Agenda Analysis
Location: the school cafeteria at the intersection of Juanita and 4th.
Formatting: I'm still working out the formatting and documents production since the District has moved to Boardbook.
English as a Second Language (ESL), item 8.1: If I am reading the data correct, the District receives only $649.00 in federal grants for 26-27. See TEA's Entitlement and Allocation Dashboards. The current Dept. of Education proposed budget for Title III funds zero's out roughly $890 million nationally for these grants. The federal law mandating that programs be provided, however, has not been repealed by Congress.
FLETCO bid approval to renovate the 1909 building, item 8.2: Once the 2024 bond monies are spent on this part of the bond build out, for the first time since 1909 this building will be dedicated to Administration only. Or, that's the plan. If the District has a growth spurt, the former classrooms in this building may become valuable as classrooms again. In any event, this contract is worth $2.6 million, according a site skimming data from the Texas Dept. of Licensing and Registration. (Time permitting, I'll go back and find original source data here.) Pay attention to this construction because not just any firm can do it - the building is recognized as historical, so their are certain legal limitations, at least on the exterior. (In my day there, it contained the school cafeteria.)
Pending - if I get access to meeting docs in advance to the meeting I will post them. Still working out the bugs with Boardbook.

B. Meeting Review
Approve Fletco bid to renovate 1909 building, item 8.2: The Board approved a $6,371,854 bid to approve renovations to the 1909 legacy building. Here is the approved bid package. I asked Gemini for some analysis:
Here is a summary of the project expense categories for the Irion County ISD 1909 Building Renovation:
• Construction Costs / Cost of Work: $5,171,524
◦ Combination Proposal (Fletco Construction, LP): $3,986,300
◦ Owner Allowances & Systems Estimates: $409,000 total (covering Roofing, Fire Sprinklers, Voice/Data Cabling, Audio Visual, Communication, Fire Alarm, Security Access, Video Cameras, and Intrusion Detection)
◦ Site & Project Support Line Items: $37,900 (includes subsurface investigation, storage trailers, SWPPP inspections, moisture testing, shipping, printing, and builder's risk insurance)
◦ Construction Contingency: $400,000
◦ Construction Management Fee & General Requirements (Cumming Gallagher): $338,324
• Fees and Owner's Direct Expenses: $476,830
◦ Architectural & Engineering Fees (Parkhill Architects): $399,330 total across interior, exterior, and civil engineering
◦ Testing, Inspections, & Commissioning: $63,000 total (Material Testing/Inspection by eHT, HVAC Test & Balance and MEP Commissioning by Campos Engineering)
◦ Permits & Accessibility Reviews: $17,500 total (Building Permit/Plan Review/Inspections and TAS Reviews)
• Furniture, Fixtures, & Equipment (FF&E): $400,000
◦ FF&E Allowance Estimate: $400,000
• Miscellaneous Contingencies: $323,500
◦ Owner Move-In Estimate: $75,000
◦ Utility & Technology Allowances: $95,000 total ($15,000 Gas/Electric; $80,000 Technology)
◦ Asbestos/Hazardous Materials Survey (King Consultants): $3,500
◦ Owner Contingency: $150,000
Consent agenda, expenses, item 6: The Board approved expenses for the previous month, and here is the check register. Here is a Gemini summary:
This document is a Year-to-Date Check Register for Irion County ISD covering the period from September 1, 2026, to September 30, 2026 (Accounting Period: A, Run Date: October 9, 2026).
Financial Overview
Grand Total Disbursed: $265,360.19 across 4 pages of transactions.
Payment Methods: All listed payments were issued as checks/direct disbursements (EFT flagged as "N").
Largest Expenditures
Irion County Appraisal District: $61,609.53 (Check 028716) for the 4th-quarter apportionment.
Sonora ISD: $21,625.00 (Check 028796) for Educational Life Skills.
Fairview Accelerated: $20,164.42 (Check 028736) for a fair share agreement.
The Brokerage Store: $18,960.00 (Check 028729) for student insurance.
TXU Energy: $18,328.50 (Check 028798) for district electricity.
TASB RMF: $17,349.00 (Check 090126) for quarterly workers' compensation insurance split across instructional, maintenance, and cafeteria funds.
Arbiter Pay: $10,000.00 (Check 090726) for athletic game officials.
First Financial Bank: $9,170.10 (Check 028713) for an Ideal Impact payment plan.
Key Expenditure Categories
Instructional & Digital Curricula: Edmentum district-wide license ($5,858.00), Lowman Education renewal ($1,650.00), Lead4ward ($1,500.00 total), Amplify Education ($776.25), and Frontline Technologies ($635.00).
Athletics & Extracurriculars: Band props from Band Today ($2,071.00), Tarpley Music repairs ($3,183.73), football coach headsets from Porta Phone ($3,499.26), Perry Weather service ($4,284.00), Glasscock Co. ISD District 11-A fees ($5,000.00), UIL membership ($2,500.00), and drug testing ($2,796.00).
Operations, Utilities & Facilities: City of Mertzon water/sewer ($4,688.90), Kendrick Oil fuel ($4,399.76), Mayfield Paper custodial supplies ($4,359.98 across three orders), Thyssenkrupp elevator quarterly service ($2,027.14), and Roberts Truck Center bus repairs ($2,094.85).
Internal VISA Accounts: Routine departmental credit card statements cleared on September 24, including Administration ($535.32), Athletics ($680.18 net of an AT&T credit), Band ($1,959.30), Elementary ($35.00), and Maintenance ($949.15).
Pending

C. Commentary
2024 IC ISD Bond update: After this meeting, I visited in the parking lot with two Gallagher representatives about the stormwater runoff from the new transportation facility that was designed by Parkhill to purposefully dump into a City of Mertzon alley. Gallagher and Parkhill have taken the exact same approach with our community's 2024 school bond funds that architect Jeffrey Potter and WBK Construction took with the construction of City Gym in 2019. They are by design dumping stormwater runoff into a public right of way and looking the other way as property owners and the City of Mertzon get flooded. I'll change my opinion on this when I see the design plans, which I have previously requested many times, that direct the stormwater coming off the transportation facility into the new stormwater detention area nearby. Gallagher and Parkhill need to be better corporate citizens and stop intentionally flooding local government and property owners.
765 kV update: We are in a holding pattern for the line proposed thru Irion County, as well as the line east that goes from Eldorado to Belton. You can find my latest filings over at my 765 kV Documents page. We had a briefing deadline last week for two very specific remanded issues related to whether Oncor and LCRA had proven up that they needed the line. The Administrative Law Judges must now write an amended Proposal for Decision, and then there's yet another briefing period where the Intervenors get to take issue with that decision. And, after that, it has to be scheduled for public meeting for oral argument and decision by the PUC Commissioners. There is also a separate appeal to the PUC Commissioners, the Kennedy appeal, that has yet to be decided. For those in favor of stalling the case until the next legislative session starts in January, my guess is they will get their wish. Also, keep in mind the Texas Senate Business and Commerce Committee has an interim charge to report on, so before long (but probably not before the mid term elections) we should have some legislative recommendations.
I have a habit of reviewing the IC ISD bidding documents over at the Gallgher website. I recently found this gem buried deep in one of the documents:

I don't think this data is entirely accurate...the rain storms are intensifying. And, street flooding around Mertzon happens even at 1" of rain. In any event, I'm going to continue to pay my flood insurance premium, especially in light of my comments at 1 above.
4. I am simultaneously dealing with three eminent domain matters (Matterhorn pipeline, Eiger pipeline and Oncor/LCRA 765 kV transmission line) and one inverse condemnation matter (Irion County ISD). Were I not a lawyer able to represent myself, my legal bills would be through the roof. Our state legislature, Governor, Lt. Governor and local government are not property owner friendly. The next time you hear about what a great place Texas is and how business friendly it is, factor this in: the rural landscape is being raped.
5. Pending

Copyright 2026 G. Noelke